JKPDD CURTAILMENT PROGRAMME WINTER 2016 (METERED / NON-METERED CONSUMERS)
GOVERNMENT OF JAMMU AND KASHMIR
Office of the Chief Engineer EM&RE Wing Kashmir
CURTAILMENT PROGRAMME – WINTER 2016 (NON-METERED CONSUMERS)
| TIMING | NON METERED | |
| MORNING | 05.00 AM TO 08.00 AM | TWICE A WEEK “OFF” |
| DAY | 08.00 AM TO 01.00 PM | THRICE A WEEK “OFF” |
| 01.00 AM TO 06.00 PM | FOUR TIMES A WEEK “OFF” | |
| EVENING | 06.00 PM TO 10.00 PM | TWICE A WEEK “OFF” |
| NIGHT | 10.00 PM TO 05.00 PM | ONCE A WEEK “OFF” |
CURTAILMENT HOURS PER WEEK / DAY
Advertisement
| TIMING | NON-METERED | |
| MORNING | 05:00 AM-08:00 AM | 6 |
| DAY | 08:00 AM-01:00 PM | 15 |
| 01:00 PM-06:00 PM | 20 | |
| EVENING | 06:00 PM-10:00 PM | 8 |
| NIGHT | 10:00 PM-05:00 AM | 7 |
| TOTAL HRS/WEEK | 56 | |
| AVERAGE HRS / DAY | 8.00 | |
- All essential loads will remain “ON” during curtailment hours
- During peak hours, there are instances, when the total load on the system exceeds to such levels which are beyond the entitled power quota. Accordingly, unscheduled cuts are enforced. However, efforts are made to restrict these cuts to minimum time durations possible. In addition, certain technical constraints of 33KV feeders, Receiving Stations and Grid Stations in some areas also necessitate unscheduled cuts.
CURTAILMENT PROGRAMME WINTER 2016 (METERED CONSUMERS)
| TIMING | METERED | |
| MORNING | 06.00 AM TO 10.00 AM | ONE HOUR DAILY |
| DAY | 10.00 AM TO 06.00 PM | TWO HOURS DAILY |
| EVENING | 06.00 PM TO 11.00 PM | ONE HOUR DAILY |
CURTAILMENT HOURS PER WEEK / DAY
| TIMI | NG | METERED |
| MORNING | 06.00 AM-10.00 AM | 7 |
| DAY | 10.00 AM-06.00 PM | 14 |
| EVENING | 06.00 PM-11.00 PM | 7 |
| TOTAL HRS / WEEK | 28 | |
| AVERAGE HRS / DAY | 4.00 |
NOTE:
- All essential loads will remain “ON” during curtailment hours
- During peak hours, there are instances, when the total load on the system exceeds to such levels which are beyond the entitled power quota. Accordingly, unscheduled cuts are enforced. However, efforts are made to restrict these cuts to minimum time durations possible. In addition, certain technical constraints of 33KV feeders, Receiving Stations and Grid Stations in some areas also necessitate unscheduled cuts.
JOIN TELEGRAM | INSTAGRAM | ANDROID APP
Attention Please :
Looking for Govt or Private Job?
Click here to Install Our Official Mobile App to Get Regular Jobs Updates, Breaking News, Results & Current Affairs
Advertisement
More Jobs in Jammu and Kashmir
- NHIDCL Jobs Recruitment 2025.
- ITBP Jobs Recruitment 2025.
- SBI Recruitment 2025 Specialist Cadre Officers posts.
- BEL Recruitment 2025 52 posts.
- DRDO DIHAR JRF and RA Recruitment 2025.
- Territorial Army Recruitment Rally 2025 166 posts.
- SEBI Recruitment 2025
Advertisement
Do you Need Website, Mobile App or Software check our Services Below
Websites & Mobile Apps |
Softwares |